Editing a schedule does not save changes

  • 7013336
  • 19-Sep-2013
  • 19-Sep-2013

Environment

NetIQ Secure Configuration Manager 5.9
NetIQ Secure Configuration Manager 5.9.1

Situation

When an existing schedule is edited, it does not save the changes.  The scheduled job continues to run according to the original settings.  It is also not possible to schedule a new job for a specific time.  It always runs an hour after the created the schedule.

Resolution

1. Close the SCM Console.

2. Rename the current NetIQ.VM.CustomCheckTemplate.dll from C:\Program Files (x86)\NetIQ\Secure Configuration Manager\VSOC

3. Download the NetIQ.VM.CustomCheckTemplate.dll from ftp://tsdownload:yellow&77down@ftp.netiq.com/download/Products/SCM/SCM591/ScheduleFix/ScheduleFix.zip and copy it to C:\Program Files (x86)\NetIQ\Secure Configuration Manager\VSOC.

4. Start the Console. 



Cause

Core services was not passing the modified value [Next_Run_Date] to the database