This document (7013336) is provided subject to the disclaimer at the end of this document.


NetIQ Secure Configuration Manager 5.9
NetIQ Secure Configuration Manager 5.9.1


When an existing schedule is edited, it does not save the changes.  The scheduled job continues to run according to the original settings.  It is also not possible to schedule a new job for a specific time.  It always runs an hour after the created the schedule.


1. Close the SCM Console.

2. Rename the current NetIQ.VM.CustomCheckTemplate.dll from C:\Program Files (x86)\NetIQ\Secure Configuration Manager\VSOC

3. Download the NetIQ.VM.CustomCheckTemplate.dll from ftp://tsdownload:yellow&77down@ftp.netiq.com/download/Products/SCM/SCM591/ScheduleFix/ScheduleFix.zip and copy it to C:\Program Files (x86)\NetIQ\Secure Configuration Manager\VSOC.

4. Start the Console. 


Core services was not passing the modified value [Next_Run_Date] to the database


This Support Knowledgebase provides a valuable tool for NetIQ/Novell/SUSE customers and parties interested in our products and solutions to acquire information, ideas and learn from one another. Materials are provided for informational, personal or non-commercial use within your organization and are presented "AS IS" WITHOUT WARRANTY OF ANY KIND.

  • Document ID:7013336
  • Creation Date:19-SEP-13
  • Modified Date:19-SEP-13
    • NetIQSecure Configuration Manager

Did this document solve your problem? Provide Feedback