Weekly and daily scheduled jobs do not save and apply the updated recurrence time schedule

  • 7017956
  • 16-Aug-2016
  • 16-Aug-2016

Environment

NetIQ Secure Configuration Manager 6.1

Situation

When an existing weekly or daily scheduled job is edited for recurrence time schedule and then saved, Secure Configuration Manager does not save and apply the updated recurrence schedule. The next run date is not updated as per the updated recurrence schedule

Resolution

To work around this issue, delete the scheduled job you intend to update and create a new scheduled job with the same parameters but with the new, intended recurrence time schedule.