Scheduled Incremental Jobs not running after Daylight savings time changed

  • 7018818
  • 20-Apr-2017
  • 10-May-2017

Environment

PlateSpin Protect 11.2

Situation

This article discusses about Scheduled incremental jobs are not running after Daylight savings time changed.

Resolution

Following steps are recommended to resolve the issue:

1.  Go to the Protect web console
2.  Remove the workload but don’t delete the virtual machine and don’t remove the components.
3.  Re add the workload
4.  Run a full job first
5.  Run an incremental job after that he scheduled job will run.