Application with pre-install schedule runs on the wrong day

  • 3574101
  • 20-Apr-2007
  • 30-Apr-2012

Environment

Novell ZENworks 7 Desktop Management Support Pack 1 - ZDM7 SP1 Application Launcher (NAL)

Situation

If an application is set up for pre-install, and a range of days is chosen, plus some days of the week are deselected (i.e., it's not set to run every day), then the days of the week will take precedence, the date range is ignored.

Resolution

Fixed in ZENworks 7 Desktop Management Service Pack 1 Interim Release 3a, available at https://download.novell.com

Additional Information

The problem does not occur if all days of the week are left selected.