Returns checklist information on an item. In GroupWise 8.0, the checklist folder was renamed the Tasklist folder.
<ChecklistInfo> <sequence type="unsignedInt"/> <dueDate value="dateTime"/> <percentComplete type="int"/> <completed type="dateTime"/> <thread type="string"/>
Specifies the order of the item in the checklist.
Specifies the date the item is due.
Tasklist items can be marked with a percent complete value of 0-100%.
The completed field is the date and time in UTC that the item was marked complete. If an item is marked complete, the percentComplete is automatically changed to 100%.
This read-only field specifies the indentation level for sub-tasks. For example, if you have two values separated by a colon (“:”)(for example. 13D5:13FF), it means the item is indented one level. If there are two colones, it means the indentation is two levels.